Wednesday

Reason of negative float in construction schedule software

If you are using construction scheduling software likewise primavera, MS Project or FastTrack Schedule. You face negative float during scheduling. you will commit that the fact activities with constrained dates affecting on the construction project planning process, however, the method of applying these constraints may cause confusion to the project schedule if we used the imposing tasks to must finish/start by and no later than in baseline project plan.

In terms of constraint in Primavera, it creates the negative float. However before we attempt to make any adjustment to Lags in the schedule, the appropriate suggestion would be that you should recheck all activities & observe why there is a need for it. There might be a reason why it is being used. If the only reason for using Lags is to suppress float, thus making the activity critical, then lags should be removed and it must show the real logic in the schedule.

Remember that:
1) Imperative linking of activities causes artificial negative floats in the schedule if activities are FS (Finish To Start) linked to each other will tend to push the project finish date to an else finish date.
2) The Project Setting "Must Finish By", should be checked if there's a date outpaced.





AMIR RANA, BSC Civil Engineer
Civil Engineer expertise in planning, Project controls & Management for numerous construction projects for reputed clients.

Planned, executed and managed various medium to large size construction projects.
Excellent leadership qualities with high command in communication & interpersonal skills and strong analytical, team building, problem-solving and organizational abilities; proficient in working in a computerized environment.

Skilled in the preparation of project & tender program.
Experienced in the utilization of the Critical Path Method analysis, (Extension of time Claims)EOT and recovery schedules, Progress reports, S-curves, Earned Value Analysis, Claims & Delay Analysis. 

Tuesday

RFX Documents, Know the Difference Between RFI, RFQ and RFP

Do you know! what is RFX?

We were often asked from our readers what is the difference is between a Request for Information (RFI), a Request for Proposal (RFP) and a Request for Quote (RFQ).

These terms are properly used in official documentation.

"RFX" is a term used, to refer to all 'Request For…' documents used to solicit responses, of various types, from suppliers. 

The three common documents are:

Request for Information (RFI)
Request for Proposal (RFP)
Request for Quote (RFQ)

According to our experts the differences between RFQ's, RFI's and RFP's are as follows:

Request for Information (RFI)

An RFI is generally used when the solution to a business problem is not immediately evident or clearly defined. The RFI is used to gather information, NOT to make a selection or an award.
The Supply Chain Management Unit works with the Customer to:

Clearly, describe the problem;
Solicit external expertise regarding how to solve the problem;
Study proposed solutions.

Request for Proposal (RFP)

An RFQ is used when the Customer understands the business problem and what's needed to solve it, including specifications and procedures. Price is usually not the determining factor in the evaluation of an RFP. Factors such as quality, service, and reputation are also taken into consideration.

Request for Quote (RFQ)

An RFQ is generally used to obtain pricing, delivery information, terms and conditions from suppliers. In this case, requestors have a clear understanding of what they need, including requirements and specifications. To procure the exact product or service needed, the Customer provides the Supply Chain Management Unit with as much information as possible, including complete specifications, quantities, and delivery schedule.

The common thread between all three types of "RFX" documents is that the Customer/Government Entity is not obliged to appoint a service provider on the results from issuing any of these requests. The best way to know that a tender award will be made is when you respond to a formal quotation or a competitive bid.
difference between a baseline schedule and a current schedule
master schedule vs baseline schedule
what is the baseline schedule when should it be changed
scope baseline
how to develop baseline schedule
what is baseline
preliminary baseline schedule
schedule baseline purpose
To learn all you need to know to respond to tenders correctly, and hopefully successfully attend our How-to-Tender workshops. Visit our website to find out more and to register. For more information on the tender courses please email

AddToAny